Preparation work
Remove display unit - Centre
| | | Care Point: | Protect display unit.
|
| | | 1. | | | | 2. | Partially remove display unit (2).
| | | 3. | Disconnect electrical connectors.
| | | 4. | Remove display unit (2).
| | | 
|
Install display unit - Centre
| 1. | Install components in reverse order.
| | | | | Care Point: | Carry out steps 2 to 15 if a new control unit is fitted.
|
| Care Point: | Make sure VCI and MDS batteries are in good condition or connected to external power supply.
|
| | | 2. | Connect McLaren Diagnostic System (MDS).
| | | 3. | Proceed to Diagnostic Toolbox within Advanced Driver Interface (ADI).
| | | | | Care Point: | If update is not available, proceed to step 10.
|
| Care Point: | Do not attempt to start reprogramming until the Ethernet cable is installed correctly.
The OBD2 cable must remain connected to the vehicle and MDS tablet during the entire reprogramming process.
|
| | | 4. | Access Reprogramming.
| | | 5. | | | | 6. | Install the supplied Ethernet to USB male adaptor to the Ethernet cable.
| | |
|
| 7. | Plug USB adaptor into port one (P1) of the USB interface panel, located in the tunnel console.
| | | | | Care Point: | ADI screen will display "Update Preparing".
|
| | | 8. | Allow update to download to the ADI system.
| | | | | Care Point: | ADI screen will display progress bars during install, followed by "Update Successful" once complete.
|
| | | 9. | Allow update to install to the ADI system
| | | 10. | Access Sequences.
| | | 11. | Carry out Align Car Configuration sequence.
| | | 12. | Carry out Programme VIN sequence.
| | | 13. | Carry out Set Configuration Defaults sequence.
| | | 14. | Carry out Radio Configuration sequence.
| | | | | Care Point: | Where required, check and re-calibrate vehicle camera system.
|
| | | 15. | or
| | | 16. | Read out and clear error memory.
| | | 17. | Check functionality.
| | | 
|